June 30, 2009 Installation Starts On Po Valley's First Production Field
Po Valley Energy announced today the commencement of installation works on the Castello production field east of Milan.
The Italian contractor, Semat SpA, have commenced site activities today and expect to complete the civil works and plant installation within a target four-month schedule.
"All production plant and equipment has been built, factory tested and in storage awaiting completion of the 1st phase of civil works ready for installation. PVE is now in control of its development schedule for this field - a crucial hurdle for the Company" Mr Masterman said.
Castello is 78% complete and scheduled for start up in late October 2009 at an initial production capacity of 2.7 million cubic feet per day.
MEDIA CONTACTS:
Michael Masterman
Po Valley Energy
0417 851 303
John Field
Field Public Relations
(08) 8234 9555 / 0418 819 527
You can view the Next News Releases item: Thu Jul 2, 2009, Po Valley Commences Drilling Sillaro-2 Production Well
You can view the Previous News Releases item: Mon Jun 22, 2009, Po Valley Energy Advances Towards Maiden Italian Gas Production With Key Regulatory Approval
You can return to the main News Releases page, or press the Back button on your browser.