April 6, 2010
Castello (near Milan, northern Italy)
- Castello produced 5.4 million cubic metres (190 million cubic feet) in the March quarter 2010
- Average quarterly production was 59,884 metres per day (2.12
million cubic feet per day) - and is currently running at 60,000 cubic
metres per day
- Revenue from gas sales was €1.32 million (AUD1.94 million)
Sillaro (near Bologna, northern Italy)
- Sillaro surface plant reaches mechanical completion
- Plant expected to be ready for start up by 12 April 2010
- First commercial gas flows expected in late April 2010
Market and Prices
- ENI Gas Release prices increased from €0.21 per cubic metre in the
December quarter 2009 to €0.26 per cubic metre in the March quarter 2010
- Forward prices indicate that the ENI Gas Release prices will
further rise to €0.29 per cubic metre for the balance of 2010 and €0.32
per cubic metre in 2011
Finance
- Cash at bank at end of quarter €5.1 million (AUD7.6 million)
- Bank of Scotland (BOS) facility borrowing base limit was €13.8
million at the end of the March quarter with €10.3 million drawn at
quarter end
Castello
Castello First Quarter 2010 Production and Revenue:
Daily average production
|
|
59,884 cubic metres per day
|
March quarter production
|
|
5,382,676 cubic metres
|
March quarter revenue
|
|
€1.318 million
|
During the quarter Castello produced 5.38 million cubic metres of gas at
an average daily production rate of 59,884 cubic metres per day. The
plant was successfully ramped up to stable operating rates with few
issues.
Current production is running at approximately 60,000 cubic metres a day.
Daily Production Since Castello Start-Up:
Gas was delivered to our two customers, Italtrading and Elettrogas via
the SNAM pipeline meeting all gas specification requirements. Revenue
from first quarter gas sales was €1.32 million.
During the first quarter 2010 the 90 day BOS completion test was
finished and following formal certification and documentation, we expect
BOS completion test sign-off in April 2010. When the completion tests
are confirmed for both Sillaro and Castello the BOS margin over
EUROLIBOR will drop from 3% to 1.8%.
Sillaro
As previously reported, heavy snow as late as 10 March 2010 hampered progress on the final stages of surface plant installation.
Installation of the Sillaro surface plant is now on schedule to reach
mechanical completion on 6 April 2010 and ready for pre-commissioning
start-up by 12 April 2010. Final safety and environmental checks will
then be completed with the final regulatory go ahead for commissioning
start-up expected late in April 2010.
1 - Sillaro gas production plant, 10th March 2010
2 - Sillaro gas production plant, 1st April 2010
Prices
Prices rose through the March quarter with rising crude oil, diesel and
fuel oil prices, and the falling Euro, contributing to increases in
prices we receive under our ENI Gas Release referenced gas sale
contracts.
Based on forward curves for the balance of 2010 the ENI Gas Release price projections are now close to €0.30 per cubic metre.
Italian Eni Gas Release Price: March Update
Finance
Po Valley concluded the March quarter with positive operating cash flow,
cash at bank of €5.1 million (AUD7.6 million) and conservative debt
levels of €10.3 million.
Under the BOS reservoir based facility, BOS sets a borrowing limit on a
semi annual basis. The borrowing base limit is determined according to
the facility agreement and has a maximum limit of €20 million.
The BOS calculations are based on a combination of factors including gas
and oil prices, production projections based on proven reserves and
operating costs. During the quarter BOS increased the borrowing base
limit from €10.3 million to EUR13.8 million.
- END -
MEDIA CONTACTS:
Michael Masterman
Po Valley Energy
0417 851 303
Kevin Skinner
Field Public Relations
(08) 8234 9555 / 0414 822 631
Back to the list of news releases.