May 19, 2010
Po Valley Energy Limited (ASX: “PVE”) today announced that commercial
gas production had commenced at its second production field in Northern
Italy.
Production from the first of two production wells in the Sillaro field
(near Bologna) has begun and the second well is planned to be brought in
to production over the next fortnight.
Production from double completed Sillaro 2dir well was operating at its
targeted production rate of 31,200m3/day from level A and will be
increased further when level E is brought into production over the next
week. Production from Sillaro 1dir is planned to follow.
Over the next month the plant will be brought up to the planned full production rate of 110,000m3/day.
There have been no safety incidents during the installation and commissioning of the Sillaro plant.